Authority Engineer services for development, upgradation of (i) Banar-Bhopalgarh-Kuchera (SH-63) length: 126.500 km. (Package No. WB/ RSHDPII/EPC/01). (ii) Bhawi – Pipar – khimsar (SH-86C) Length 83.225 km (Package No. WB/RSHDP II/EPC/02) (iii) Jodhpur-Marwar Junction- Jojawar Highway (sh-61 & 61A) Length 119.095 km (Package No. WB/ RSHDP II/EPC/03) in the state of Rajasthan on EPC mode . Total Length – 328.82 km ; 2 lane without Paved Shoulder; Project Cost- 612.88 Crore.
Nature of project: AE Supervision
Name of Client: Rajasthan State Highways Authority , Jodhpur(Rajasthan)
Length: 328.82 Km
Estimated capital cost of Project (in Rs. crores): 612.88 Crores
Lane of Road: 2 Lane
Status: Construction Phase Completed and Operation & Maintenance inprogress
PPP / EPC / HAM / DBFOT / BOT:EPC
Duration- From March 2023 to March 2026